What is the definition of a RED risk in PPM?
Hi team. In the Status Report metrics summary I can see individual values for Overdue and Red. What is a Red risk?
Hi team. In the Status Report metrics summary I can see individual values for Overdue and Red. What is a Red risk?
We are a ServiceNow shop and we are exploring the possibility of expanding outside the typical ITSM market by offering business applications that target other, specific industries. I am wondering if anyone else has had experience marketing ServiceN...
Hello,I would like to share Investment portals with groups. However, they are not displayed in the sharing option because they do not have it_project_user role stored.Where is this setting stored?Is it possible to change this to it_demand_user?Many t...
Hi! I want to know if it is possible to add other options to the list of personalize fields for Goals & Targets. (Not Backlog) It looks like I can only select from a specific few and I can't for example add 'Strategic Priorities' as a column option. ...
Hello All, I am setting up a Rate Model for various Resource Plans. Rate Model : Role-> User Then I have set up the Rate Lines, where for various Users, I have given different Rates. Once done, I created a Demand and under it, I created a Role-ba...
We have an enhancement request from our Governance Team to flag demands that are submitted that are Proof of Concept type demands so an email can be triggered to requestor reminding them to submit their POC Implementation Analysis to the Governance T...
Hello, I would like to find out if there is an easy way to sync ADO projects to a ServiceNow project (PR Number or PRJ Number).This is after all the connections are done. Thank you and regards,Mercy
What is the best practice for schedules in RM? Are people using 8-5 weekdays, just trying to see what the majority ok folks are using
My resource manager would like to see on which tasks he doesn't have add a resource plan. How can i do a report or a dashboard to show all the tasks where my manager is responsible without ressource plan ?
Hi Community, We would like to restrict the possibility for users to submit time cards beyond the end date of the resource plan (regardless if this is Allocated or Completed). As far as I know the only scenario where a user cannot submit time card is...
Hello, I am trying to customize our OOB 'PMO Dashboard' to show all of the metrics we'd like to see at the Program level. For report widgets (single score, and chart) based on the pm_project table, they seem to work fine when checking the 'Follow int...
azure integration
Hi Everyone, May I know if it is possible to delegate a demand assessment? If so, how are we going to set this up? Regards,Diane
Hello We are wanting to change the OOB project phases to align with customers existing phases Can someone tell me what are the implications of changing these? should they be relabeled or create new ones? Do all related forms get updated ie project w...
Hi team. I am a lowly user with expanding analytics access I am in the Action record and want to be able to export the Field Changes data in the Activities field. I can export the Worknotes content, but can't find how/if I can access the Field Change...
| User | Count |
|---|---|
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 3 |