Recalculating Resource End Date Based on New Planned End Date
Is there a way to auto recalculate the resource assignment end date for multiple resources (large project with many resources) if the planned end date has been moved to an earlier date?
Is there a way to auto recalculate the resource assignment end date for multiple resources (large project with many resources) if the planned end date has been moved to an earlier date?
Hi everyone,Does anyone know about embedding an external link into a project?We use SharePoint to create requests for budget approval, which are then routed to others within the organization but external to the PMO. Is there a way to embed this type ...
HI All, As part of my project requirement, I need to implement a solution to automatically hide the swim lanes without data/cards. In OOB there is an option to uncheck the unwanted swim lanes in the advanced settings. But this solution is not feasibl...
Can anyone please explain what is the functionality of the "Funds" on the Planning console. Tried to check on community but could not find any relevant details.Thanks in advance for help. Regards,Kumar
Hi all, I am wondering which exact license is requried for the Resource Management Workspace in Yokohama.Is SPM Standard sufficient or is SPM Pro required? I am confused especially because of following 2 store resource pages:1. App "sn_rm_ws" with ve...
I have added a cost plan to a project and the total planned cost is successfully rolling up to the project . However, when I am adding this project to a program, the total planned cost does not roll up. Can someone please help me with that?
Hi Community, I’m facing an issue where the actual cost of projects is not rolling up to the program level as expected. Despite accurate data entry at the project level, the aggregated cost at the program level does not reflect these updates. I unde...
Hey all — I’m building a Service Catalog item in Tokyo (Xanadu build) and I’ve hit a wall.What I’m trying to do:I have a List Collector variable (sys_user table) where users select team members. It should only show users in the hierarchy of the Reque...
We have some projects that were setup with an expense type of Capex and after months of the project being worked as Capex we've been told it should've been set to Opex, but the PM didn't catch it. The project now has time cards, expense lines, cost ...
Hi All I have new requirement in my project . My customer wants to know if there is any integration is available between ServiceNow SPM and PACTS. If so can anyone help me with more details. ThanksSathish
Hi, OOB ServiceNow does not provide/allow the functionality of time recording against EAP planning items such as epics, features. Is there a way to implement this ? If yes, how to do we go about doing it ? Has anyone ever implemented this and is thi...
Hello,I need to add or remove fields from 'Filter' on portfolio plan in Strategic plan workspace.I am not finding where exactly these fields are configured. please respond if any one aware on this . Thanks in advance.
Hello All,In the New project workspace the status report is not available/visible for the same project but it is available/visible in the Classic project workspace. Can anyone please help me with reason.
Hi everyone, we’re currently testing SPM in a sandbox environment (newest version of Yokohama) and noticed that the L2 menu (subToolbar) does not appear in the Project Workspace, although it seems to be configured OOB (newest versions of project work...
Is there a way to auto recalculate the resource assignment end date for multiple resources (large project with many resources) if the planned end date has been moved to an earlier date? Thank you, Kaianna