Resolved! How does percent_complete increment on Project form?

I want the percent_complete field to increment if ANY closed state is selected. Right now it only increments if the Closed Complete is selected for a respective project task, ignoring Closed Incomplete and Closed Skipped.  I think it is a business ru...

MBarrott by Mega Sage
  • 1496 Views
  • 10 replies
  • 4 helpfuls

Link between State and Percent Complete in Project

Hello,How can I modify the link between the state and the percent complete fields.When I change the state to "Work In Progress", the percent compte will be 0% when I want it to keep the same value.  I would like :State "Closed skipped" or State "Clos...

Farfara_0-1711713386372.png
Farfara by Tera Contributor
  • 1018 Views
  • 6 replies
  • 0 helpfuls

Visual task board

Hi I have created data driven visual task board for custom table from admin account .When I impersonate itil user and try to open the visual task board it is showing the error like You do not have the permissions necessary to view the board. Please h...

Scenario planning

How the scenario planning connected to strategic planning workspace. What is the typical sequence and what can be reused from one to other. 

brajesh17 by Tera Contributor
  • 1450 Views
  • 4 replies
  • 6 helpfuls

Resolved! Create custom burndown charts

Hi, is there a way to customise/adatp the OOB burndown chart? It seems to work quite differently from the rest of the widgets in the platform.  Both Product Owner Dashboard and Agile Board Analytics don't seem to be standard widgets/reports in the ...

find_real_file.png find_real_file.png find_real_file.png find_real_file.png

Resource Groups and Group Resource Plans

How are others using resource groups and assigning a group to a resource plan, which is assigned to a task, and managing new resources into the group and updating the resource plan? We can't a good way of maintaining the group to resource plan relati...

DMaggio by Tera Contributor
  • 553 Views
  • 1 replies
  • 0 helpfuls

Read only fields on Parent Project Tasks

When using projects, if a project task has a child project task associated to it several fields become read only. The Project team would like to use parent/child project tasks independently for the purposes of calculating resource costs, but as the f...

SNAdmin47 by Kilo Sage
  • 1064 Views
  • 2 replies
  • 0 helpfuls

Resolved! Adding another choice for STATUS on Project task form

Hi Community, I have the following requirement from my portfolio stakeholders: add another choice in the status field from Project Task form called Complete and to appear against Blue colour when reviewed on Planning Console (Classic or New Project W...

PaulaaO by Mega Sage
  • 2621 Views
  • 10 replies
  • 2 helpfuls