Move an automation request to the Planned state

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:1分
  • After creating an automation request, move it to the Planned state before you work on it or create associated automation tasks or resources.

    始める前に

    Create an automation request. For more information, see Creating an automation request.

    Verify that the state of the automation request is New.

    Role required: sn_ac.automation_business_user, sn_ac.automation_technical_user, or sn_ac.automation_admin

    手順

    1. Navigate to All > Automation Center > Automation Center Home.
    2. Select the list icon (List icon.).
    3. On the Lists tab, under Build, select All Automation Requests.
    4. Open the automation request that you want to move to the Planned state.
    5. In the form header, select Move to Planned.

    タスクの結果

    After you move an automation request to the Planned state, it's ready for you to work on.