View default project and project task state categories
View category information for the default project and project task states. In the base system, the states in project and project task inherit the states in Task table.
Avant de commencer
Role required: admin
Procédure
- Navigate to .
-
Update the filter with the following AND conditions:
- [Table] [is] [task]
- [Column name] [is] [state]
- Run the filter.
- Select the task table, and then choose planned_task table in Dictionary Overrides related list.
Résultats
The Attributes field displays different states and the categories for a state as shown below. It also displays the default state value for each category.
close_states=3;4;7,default_close_state=3,default_work_state=2,default_open_state=1,default_skipped_state=7,default_pending_state=-5,pending_states=-5,open_states=1,work_in_progress_states=2