Create advanced task dependency using a work order template
You can create work order templates that contain advanced task dependencies.
Avant de commencer
Role required: wm_qualifier or qualifier combination role
Plugin required: Field Service Task Dependency (com.snc.fsm_task_dependency)
Pourquoi et quand exécuter cette tâche
If a work order contains multiple tasks, you can create advanced dependencies that establish a relationship between the tasks to determine the order in which tasks are performed.
You can create dependencies among tasks of the same work order template.
This table explains the types of advanced task relationships and dependencies that you can create.
| Dependency type | Description |
|---|---|
| Finish to start | Indicates that the successor (downstream) task should be started after finishing its predecessor (upstream) task. |
| Start after start | Indicates that the successor (downstream) task must be started after starting its predecessor (upstream) task. |
| Start together | Indicates that the successor (downstream) and predecessor (downstream) tasks must be started together. |