Remove a dependency

  • Release version: Xanadu
  • Updated August 1, 2024
  • 1 minute to read
  • Use the planning console to remove a dependency that is no longer necessary.

    Before you begin

    Role required: it_project_manager

    About this task

    Removing the dependency also deletes the dependency record in the Planned Task Relationship table.

    Procedure

    1. Open the project in the planning console.
    2. Do either of the following.
      OptionDescription
      On the Gantt chart
      • Right-click the relationship and then click Delete Link.
      • Double-click the relationship and then click Delete on the Planned Task Relationship form that appears.
      On the WBS list
      • Delete the value in the Predecessor column.
      • Click the value in the Predecessor column and then click Delete on the Planned Task Relationship form that appears.