Migrate operational resource plans

  • Release version: Xanadu
  • Updated August 1, 2024
  • 1 minute to read
  • Migrate the required Operational resource plans to attribute-based Operational resource assignments.

    Before you begin

    Role required: resource_manager, it_project_manager, demand_manager, admin

    Procedure

    1. Navigate to All > Resource > Resource Plans > All Operational Plans.
    2. Select the list of operational resource plans to migrate.
    3. Select Migrate resource plans from the Actions on selected rows... list.
      Operational resource plans are migrated to Operational resource assignments. You can view the list of Operational resource assignments at All > Resource > Resource Assignment > Operational Resource Assignments.