Copy a project
Another option for creating a project is to copy an existing project with all its tasks and relationships. After you specify the start date for the copy, the system adjusts all task start and end dates automatically.
Before you begin
Role required: it_project_manager
Procedure
Result
By default only the short description, planned dates and duration fields are copied from source project to the target project. If additional columns must be copied, they should be declared in the project property List of attributes that will be copied from the originating project task.