Agile 2.0 Sprint Dashboard
Summarize
Summary of Agile 2.0 Sprint Dashboard
The Agile 2.0 Sprint Dashboard in ServiceNow enables scrum masters and sprint planners to effectively track and analyze the progress of current sprint stories. Accessible viaAll > Agile Development > Dashboards, this dashboard provides critical insights into sprint status, forecasted completion, and scope changes, helping teams stay aligned with sprint goals and timelines.
Show less
Key Features
- Sprint Progress Indicators: Visual widgets display percentage of work completed, time elapsed, committed story points, and stories missing estimates. These metrics help determine if the sprint is on track.
- Scope and Estimate Tracking: Widgets highlight total planned work, committed scope, and any scope changes during the sprint to support informed decisions.
- Blocked Work Monitoring: Identifies work blocked within the sprint to address impediments promptly.
- Data Visualizations: Includes Sprint Burndown, Sprint Burnup, and Cumulative Flow Diagram reports that visualize scope changes, work completion trends, and story state transitions.
- Forecasting: Predicts likelihood of sprint completion on schedule using historical data trends for both scope and remaining work.
- Customizability: Reports and widgets such as Burnup, Burndown, and Cumulative Flow Diagram can be tailored to specific team needs.
Key Outcomes
- Improved Sprint Visibility: Scrum masters gain clear insights into sprint progress, scope fluctuations, and time management, enabling proactive adjustments.
- Better Planning and Risk Management: Forecasting tools help anticipate potential delays and scope creep, supporting timely intervention.
- Enhanced Team Productivity: Tracking blocked work and story states aids in identifying bottlenecks and accelerating story flow to completion.
- Comprehensive Reporting: Visual reports provide an at-a-glance understanding of sprint health, making it easier to communicate status to stakeholders.
Track the progress of your stories in the current sprint and forecast sprint completion using the Sprint Dashboard.
Navigate to and select Agile 2.0 Sprint Dashboard.
The Agile 2.0 Sprint Dashboard provides the following insights:
- Displays details of the sprint such as percentage of work that is complete, time elapsed, and total number of stories that are missing estimates.
- Displays the number of stories of the sprint in their current state and their progress.
- Indicates the scope changes, if any, and trends of those scope changes.
- Indicates the way the team needs to progress on stories to achieve the sprint goal.
- Forecasts data showing the likelihood of completing the sprint as planned.
End user and roles
| End user and goal | Required role | Benefits |
|---|---|---|
Scrum master and sprint planner: Need visibility into scope changes, completed and remaining work for a sprint to adjust plans to complete the sprint on time. |
scrum_user |
|
Indicators
- Scrum: Sum of story points of all stories in the current sprint
Generates the scope series in the Sprint Burndown and Burnup reports. The scope series indicates the amount of work (in story points) that is the planned for the sprint.
- Scrum: Sum of story points of active stories in the current sprint
Generates the completed series in the Sprint Burndown and Burnup reports. The completed series indicates the amount of work (in story points) completed in the sprint.
- Scrum: Time elapsed in sprint
Calculates the time to be displayed in the Time Elapsed widget.
- Scrum: Count of all stories in the current sprint
Generates the area series in the Sprint Cumulative Flow Diagram report. It indicates the number of stories in the current sprint.
- Scrum: Percent Completed by Points
- Calculates the amount of work (in percentage) completed for the sprint. The value is the result of the following formula:
([[Scrum: Sum of story points of completed stories in current sprint]]/[[Scrum: Sum of story points of all stories in the current sprint]]*100)
Breakdowns
- Scrum: Sprint
- Scrum: Current Sprint
- Scrum: State
Widgets
- Scope
Indicates the amount of work in story points that is planned for the sprint. This widget lets you see at a glance how much work must be completed to achieve the sprint goal. It also lets you drill down to detail on the stories planned into the sprint.
- Percent Completed
Indicates the percentage of work that has been completed in the sprint using story points. This widget lets you see at a glance how much work has been completed in the sprint. Together with the adjacent Time Elapsed widget, these widgets let you easily see whether you are completing work at a rate consistent with achieving the sprint goal on schedule.
- Time Elapsed
Indicates the percentage of time that has elapsed between the start date and planned end date of the sprint. Together with the adjacent Percent Completed widget, these widgets let you easily see whether you are completing work at a rate consistent with achieving the sprint goal on schedule.
- Committed Points
Indicates the committed scope (in number of story points) of the sprint. Together with the adjacent Scope widget, these widgets let you see difference between the scope committed at the start of the sprint and the current scope of the sprint.
Note:This widget is not visible by default. You can add it from Reports to your dashboard. For more information, see Edit a responsive dashboard.- Missing Estimates
- Indicates the total number of stories in the sprint that are missing estimates. It is required that you use estimates for the other indicators, widgets, and reports on this dashboard to be meaningful.Tip:If you do not estimate stories, enter a "1" in the Story Points field. The other indicators, widgets, and reports will then effectively function by count.
- Blocked Work
Indicates the amount of work (in story points) in the sprint that is blocked.
Data visualizations
- Sprint Burnup
- Sprint Cumulative Flow Diagram
| Title | Type | Description |
|---|---|---|
Sprint Burndown |
Line |
Indicates the scope changes, if any, and trends of those scope changes. Indicates the ideal pace of work, how much work is remaining, and if the scope is likely to be completed before the end of the sprint. The Sprint Burndown report comprises the following series that can be hidden or
displayed based on your preference:
|
Sprint Burnup |
Line |
Shows the sprint burnup trend indicating scope changes. Forecasts future changes in scope and the trend of work completion. The Sprint Burnup report comprises the following series that can be hidden or displayed
based on your preference:
|
Sprint Cumulative Flow Diagram |
Area |
Monitor the progress of all the stories of your sprint between its actual start and end dates. View the number of stories in each state by their arrival to a state, time in this state, and its departure from this state. The Sprint Cumulative Flow Diagram report comprises the following areas that can be
hidden or displayed based on your preference:
Note: Stories in Ready and Cancelled states are not included in this report. |
You can customize the Burnup, Burndown, and Cumulative Flow Diagram reports. For more information, see Customizing Agile 2.0 dashboard reports.