Create or edit expense lines to capture the actuals costs. You can associate the expense lines with a cost plan or create standalone expense lines to record unplanned expenses.
Before you begin
Role required: sn_align_ws.spw_financial_user
About this task
An expense line is part of the project cost plans that can be associated with a specific source. You can create multiple expense lines for a cost plan. Only the expense lines that are in the processed state are considered
for roll ups on the work item.For unplanned expense lines which are not associated to any cost plan, system automatically creates an cost plan or associates to an existing system generated cost plan of the same expense
type.
Procedure
-
Navigate to and select portfolio plan.
-
Select a planning item from the Planning module.
-
Select the Financials tab.
-
Use one of the following options to add an expense line.
| Choice | Description |
|---|
| Select a cost plan |
- Select the actuals value from a cost plan.
- In the Expense lines side panel, select New.
|
| Select options |
- Select the options
from a cell.
- Select Add expense lines.
|
| Select new expense line option |
Select New expense line using the More actions option. Note: Use this option to record and calculate any unplanned expenses. |
-
On the Create expense line form, fill the fields.
-
Select Save.
Note: The expense lines created for sub projects can be viewed in the Cost screen of the parent project.
-
To edit a cost plan from the finanicals record page, select the actuals value from the cost plan to ex[open the Expense line side panel.
-
Select the expense you want to edit.
-