Resource Allocation form
Summarize
Summary of Resource Allocation form
The Resource Allocation form in ServiceNow enables precise management of resource assignments within a project or demand. It ensures resource allocations are tracked with accurate start and end dates, aligned with the overall resource plan. This form is essential for confirming and allocating hours, calculating planned and confirmed costs, and handling multi-currency scenarios when applicable.
Show less
Key Features
- Start and End Date: Defines the allocation period, which must be within the resource plan’s timeline.
- Resource Selection: Filters available resources based on group, role, or user specified in the resource plan.
- Confirmed/Allocated Hours: Displays hours confirmed or allocated to the resource, which roll up to the resource plan for consolidated tracking.
- FTE and Person Days: Supports different allocation units depending on the Request type selected on the resource plan.
- Planned and Confirmed/Allocated Costs: Calculates costs based on hours and hourly rates sourced from the resource plan, rate models, labor rate cards, or system defaults. These costs roll up to the resource plan as well.
- Multi-Currency Support: Displays confirmed/allocated costs in demand or project currency when the PPM Standard Multicurrency plugin is enabled and relevant views are activated.
- Form Configuration: Some cost fields are not visible by default and require form customization to be added for visibility.
Key Outcomes
By using the Resource Allocation form, ServiceNow customers can accurately assign resources within defined timelines and track both time and cost commitments. The form’s integration with rate models and cost calculations ensures financial accuracy and transparency, while multi-currency support accommodates global project needs. This results in improved resource planning, budgeting, and reporting aligned with project and demand objectives.
Use the Resource Allocation form to resource allocations.
| Field | Description |
|---|---|
| Start date | Start date for the resource allocation. The start and end dates must fall within the dates of the resource plan. |
| End date | End date for the resource allocation. |
| Resource | Resource to be allocated. The lookup results are filtered by the group, role, or user selected on the resource plan. |
| Confirmed/Allocated hours | Number of hours that the system confirms or allocates to the resource when the resource plan is confirmed or allocated. Confirmed and allocated hours roll up to the Confirmed/Allocated hours field on the resource plan. |
| FTE | Number of units for the full-time equivalent selection. This option appears if you selected FTE for the Request type field on the resource plan. |
| Person Days | Number of units for the person days selection. This option appears if you selected Person Days for the Request type field on the resource plan. |
| Planned cost | Planned cost of the resource. Planned Cost = Planned hours * hourly rateThe hourly rate is derived from one of the following sources:
Planned costs roll up to the Planned cost field on the resource plan. The field is not visible on the form by default. Configure the form to add this field if it is not visible. |
| Confirmed/Allocated cost | Cost of the resource.
The hourly rate is derived from one of the following sources:
Confirmed and allocated costs roll up to the Confirmed/Allocated cost field on the resource plan. The field is not visible on the form by default. Configure the form to add this field if it is not visible. |
| Confirmed/Allocated cost in demand currency | Confirmed/Allocated cost of a demand task in demand currency when the PPM Standard Multicurrency (com.snc.ppm_multicurrency) plugin is activated and Demand Currency view is enabled. |
| Confirmed/Allocated cost in project currency | Confirmed/Allocated cost of a project task in project currency when the PPM Standard Multicurrency (com.snc.ppm_multicurrency) plugin is activated and Project Currency view is enabled. |