Complete a resource plan from a project, planning console, or demand record
If a project or a project task is marked Closed, the project manager can complete the associated Allocated resource plans. Similarly, the demand manager can complete the resource plans for a Closed or Deferred demand.
Before you begin
The resource plan to be completed must be in the Allocated state.
Role required: it_project_manager or it_demand_manager
About this task
When a project or a project task moves to Closed Complete, Closed Incomplete or Closed Skipped state, the system prompts a message on the project and project task forms, and in the planning console for completing the Allocated resource plans if the following conditions is met.
- Corresponding resource plan is in the Allocated state.
- Resource plan start date is less than or equal to the project or task actual end date.
A similar message for completing the resource plans appears on the Demand form when a demand moves to Closed or Deferred state.
Procedure
Result
- The selected resource plan moves to the Completed state.
- If the completion date is earlier than the resource plan end date, the end date of the resource plan is updated with the completion date. If the completion date was entered later than the resource plan end date, the resource plan end date is retained.
- All the requested and resource allocations for the resource plan that are past the completion date are deleted. If there are any actual hours logged against an allocation, that allocation record is not deleted. But the allocated hours become zero and the actual hours are retained. The available and allocated hours for the resources are also updated in the aggregate tables.