Update a project using a Microsoft Project file
Import project data, from a Microsoft Project file, into an existing project in your ServiceNow instance using the Project form or Planning Console.
Before you begin
Create a project.
Role required: it_project_managerProcedure
- Navigate to .
- Open the project which you want to update.
-
Import the Microsoft Project file to update the selected project from any of
the following screens:
- In the Project form, select Import from MS Project from the context menu.
- In the Planning Console, click the more actions icon (
) and select the Import from MS Project option.
-
In the Microsoft Project Import dialog box, select the Microsoft Project file
and calculation type:
- Click Import.
Result
- A project task that was imported in the ServiceNow instance earlier and has associated time cards, resource plans, cost plan, benefit plan, or expense lines is retained on reimport even if it is deleted from Microsoft Project.
- Dates in the ServiceNow project remain same as the dates in the Microsoft Project file.
- In a ServiceNow project with subprojects, the following
details change:
- The WBS order of imported tasks is regenerated after import.
- The Planned Start Date and Planned End Date of the parent project are rolled up.
- The State of the parent project and tasks are rolled up.
- The % Complete on the top task is rolled up.