Track progress

  • Release version: Xanadu
  • Updated August 1, 2024
  • 1 minute to read
  • Track the progress of an agile phase from the Project Workbench timeline.

    Before you begin

    Role required: none

    About this task

    Stories are assigned to a project and are tied to an agile development phase in the Project Workbench. As stories are completed, the story points and the story status get rolled up to the sprint and project phase. In turn, the phase gets rolled up to the project.

    Procedure

    1. Navigate to the Project Workbench timeline.
    2. The color in the phase bar increases to show progress and the Percentage complete field is updated.