Add external dependencies between projects from Project Workspace
Set up a dependency between tasks of different projects using the new Project Workspace.
Before you begin
Role required: it_project_manager
About this task
External dependencies help you understand the impact on project schedules when there is a change in the predecessor task. Use the row context menu of your project task to add a dependency from the task of a different project.
Procedure
Result
- Dependency is created for the tasks of the two projects.
- The short description of your project is greyed out and is renamed to indicate the external dependency in the format of External project name: External task name
- A link icon (
) is added to the short description cell of the task, to indicate the dependency.
What to do next
You can navigate to the external project directly from the current project to view the status or update the details of the predecessor task. From the row context menu of the dependent task, select View project.