Create operational resource assignments

  • Release version: Xanadu
  • Updated August 1, 2024
  • 1 minute to read
  • Create operational resource assignments to allocate a portion of team or resource capacity for operational work such as administration work, meetings, trainings, and so on.

    Before you begin

    Role required: resource_user, resource_manager, it_project_manager, demand_manager, admin

    Procedure

    1. Navigate to All > Resource Assignment > Create Operational Resource Assignments.
    2. On the Resource Assignment form, fill in the fields.
      For a description of the field names, see Resource assignment form.
    3. Select Submit.

    Result

    Operational resource assignment is created. You can navigate to All > Resource Assignment > Operational Resource Assignments view the list of operational resource assignments.