Migrate financial baselines of projects to Next Experience
Migrate the financial baselines of your project to Next Experience to manage the financial using Project Workspace.
About this task
Next Experience uses new data model which has two new tables Investment Baselines (sn_invst_pln_invst_investment_baseline) and Investment Baseline Header (sn_invst_pln_invst_investment_baseline_header) which are used to capture financial baselines. The financial baselines created for demands in classic experience are not visible in Next Experience. You can migrate the existing baselines from classic to Next Experience as an on-demand activity for the required projects, or as bulk by activating and running a scheduled job.
Baselines view in the Next Experience provides better insights to view and analyze the financial performance of your projects.
Unlike the financial baselines created using Next Experience, the financial baselines created in the Classic UI do not capture the actual expenses along with planned costs as a default behavior. To have relevant information for baselines comparison, the actual costs will be captured as part of the baseline migration using the processed expense lines as of the baseline creation date of the financial baseline.
Before you begin
Role required: it_project_manager
Procedure
Result
Financial baselines for the selected projects will be migrated to Next Experience and you can view them in the Baseline view.
What to do next
View and compare the migrated baselines with any existing baselines or current baseline ().