Close a project
Closing the project involves more than just changing the project state to closed.
Before you begin
Role required: it_project_manager
About this task
Post-project activities include viewing baselines and actual values to evaluate how much the project slipped from its original estimates. They also include following up on related incidents, problems, or changes that are linked to the project through the instance.
When you close a project, all project tasks and sub-projects associated with the project are closed automatically. Normally, you should not reopen a project after it is closed. Updating the project state from Closed to Work In Progress, Pending, or Open is not allowed. If you still need to reopen a closed project, reopen an existing project task or add a new task to the project. This action for a task moves the project from Closed to Work in Progress state without affecting the other closed tasks.
You can cancel the associated future resource plans and complete the allocated resource plans for a closed project.
Procedure
Result
What to do next
- Cancel the resource plans associated with the project in any of the
following conditions:
- There is a corresponding resource plan in the Confirmed, Planning, or Requested state.
- There is a resource plan in the Allocated state with the start date later than the project end date.
- Complete the resource plans associated with the project in the
following conditions:
- There is a corresponding resource plan in the Allocated state.
- The start date of the resource plan is on or before the actual end date of the project or task.