Update the resource allocation in a heatmap

  • Release version: Yokohama
  • Updated January 30, 2025
  • 2 minutes to read
  • Use the allocation heatmap capability in Project Workspace to view and update the resource allocation.

    Before you begin

    Role required: it_project_manager

    About this task

    The Allocation heatmap toggle button provides a detailed breakdown of the allocation of an individual resource. The allocation heatmap represents the total utilization of a resource for a week or month. By default, allocation information is displayed for the week. This information helps project managers to plan their resources effectively at the project or task level.

    Integrate your ServiceNow® instance with your organization's Microsoft Teams to enable collaboration of your projects and resource allocations in Microsoft Teams. With the Microsoft Teams integration, you can communicate with the project team members and share real-time updates on the project and resource allocation status. For more information, see Setting up PPM collaboration for Microsoft Teams.

    Within the Resource Allocation view, the Approved state is prioritized and listed first, followed by other statuses based on their order in the record list. Additionally, if a user has no capacity during a given period, the corresponding cell is displayed in red color.

    Procedure

    1. Create resource assignments using Project Workspace.
    2. View the resource allocations in the heatmap by enabling the Allocation heatmap toggle button.
      You can switch from the week view to the month view based on your requirement.
    3. Edit the desired field and select anywhere on the data grid to save the details.
      Work allocation is based on capacity. The allocations are color-coded to display the availability of the resources as shown here. These colors help to identify the availability of the resource for a particular task.
      heatmap -legend
    4. Edit the resource allocation window by selecting the allocation hours cell.
      allocation-hours-cell

      Enable the Show actuals toggle to view the actuals of each resource. The actuals can't be edited from Project Workspace.

    5. From the resource allocation window, view and track the assigned Project, Owner,Task, and Task effort of a resource.

      The resource allocation is made according to the schedule of the resource, provided that the resource has a schedule.

      The Allocation heatmap modal provides the Resource status, Remaining capacity, and Utilization columns to support resource managers in evaluating task efforts.

    6. Send a direct message to the project owner on Microsoft Teams by selecting the Project Owner field.
      resource-allocation-window
      Note:
      The Project Owner field can only be selected if your ServiceNow® instance is integrated with your organization's Microsoft Teams. Resource assignments on demands are visible in the allocation window both before and after they become projects.