Manage budget of your planning items in Strategic Planning

  • Release version: Yokohama
  • Updated January 30, 2025
  • 1 minute to read
  • Allocate, manage, and approve budget for your projects. Lean budgeting allocates budget for short planning cycles across fiscal periods, such as monthly, quarterly, or yearly. This approach differs from allocating budget to the complete duration of a planning item.

    Before you begin

    About this task

    Procedure

    1. Navigate to Workspaces > Strategic Planning Workspace and select portfolio plan.
    2. Select a planning item from the Planning module.
    3. Select the Financials tab.
    4. Use the Display mode list and select Budget allocation.
    5. Manage budget using one of the following ways for the selected time scale at monthly, quarterly, or yearly level.
      • Double-click each cell in the Budget column to manually enter the value.
      • Select Copy cost as budget from the Budget column options to copy Forecast value as budget.
      Note:
      Negative budget amounts are supported. If you enter a negative Capex Budget or Opex Budget amount, or the associated cost plan has a negative total planned cost, the project budget is still distributed across the cost plan breakdowns and rolled up to the project financials.
      • You can edit the budget values using the in-grid editing feature after copying Forecast to budget.
      • Unapproved budget values are indicated with Tick mark in a circle representing the unapproved budget icon.
    6. Select Approve budget (Approve budget button.).
      Approve budget confirmation window is displayed. The Create a financial baseline for this budget approval option is enabled by default which captures the latest budget and financial estimates.
      Tip:
      The financial baseline created while approving the budget can be compared with the future baselines once the actual expenses are captured to track financial performance.
    7. On the confirmation window, select Approve (Approve button.).

    Result

    Budget widget is updated to reflect the latest approved budget. Project Manager can view the approved budget and compare it with the planned costs using the budget vs cost view by cost type.