Work plan schedule fields for Enterprise Asset Management
Summarize
Summary of Work plan schedule fields for Enterprise Asset Management
This content explains the key fields and configurations for setting up work plan schedules within the ServiceNow Enterprise Asset Management (EAM) application. These configurations enable customers to automate and control when and how maintenance or other planned work is triggered on enterprise assets.
Show less
Planned Work Schedule Fields
- Name: Specifies the name of the work plan schedule.
- Short description: Provides a brief explanation of the work plan schedule.
- Trigger: Defines the condition that triggers the work plan to run. Options include:
- Duration: Runs based on a time interval.
- Meter: Runs based on a specific asset field value.
- Condition: Runs based on filter conditions.
- Script: Runs based on advanced scripted criteria.
- Duration or Meter: Runs when either time or meter condition is met first.
- Active: Indicates if the schedule is currently active.
Trigger Details Sections
Depending on the Trigger type selected, additional detail sections appear:
- Duration Details: Configure how frequently the work plan runs (interval, weekly, monthly, annually, etc.) and specify exact timing such as days, weeks, or months. Includes options for lead time and whether to preserve calculated intervals.
- Meter Details: Define which enterprise asset field and value trigger the work plan and whether to preserve meter calculations.
- Condition Details: Set filter conditions using logical operators (and/or) to specify when the work plan should trigger based on asset attributes.
- Script Details: Enter custom scripts for advanced triggering logic.
Effectivity Details
- Start planned schedule on: Choose how the start date is determined, either by specific date, field value, or another schedule.
- End planned schedule on: Define when the work plan schedule ends.
Practical Value for ServiceNow Customers
Understanding and configuring these fields allow customers to set precise, automated maintenance schedules tailored to their asset management needs. This ensures timely maintenance, reduces downtime, and improves asset lifecycle management by triggering work plans based on time intervals, asset usage metrics, conditions, or custom logic.
A detailed description of all the work plan schedule fields in the Enterprise Asset Management application.
Planned Work Schedule
| Field | Description |
|---|---|
| Name | Name of the work plan schedule. |
| Short description | Brief description of the work plan schedule. |
| Trigger |
Trigger that specifies the type of conditions that must be met for the work plan to run. Select one of the following options:
|
| Active | Option that indicates if the work plan schedule is active. |
Duration Details
| Field | Description |
|---|---|
| Trigger type |
Frequency at which you want the work plan to run. Select one of the following options:
|
| Lead time | Number of days required for the scheduled work plan. |
| Preserve calculated interval |
Option to restart the interval calculation from the time when the work order was completed. This check box appears when Interval, Monthly, or Annually is selected for Trigger type and Fixed is selected for the Monthly type and Annually type field. |
Meter Details
| Field | Description |
|---|---|
| Field | Enterprise asset field that you want to match against to trigger the work plan to run. |
| Every | Field value that an enterprise asset must match to trigger the work plan to run. |
| Preserve calculated meter |
Option to restart the meter calculation based on the value defined in the Every field. |
Condition Details
| Field | Description |
|---|---|
| Filter Condition |
Filter conditions that trigger the work plan to run You can add multiple filter conditions to the trigger using the following options:
|
Script Details
| Field | Description |
|---|---|
| Script | Script specifying the advanced criteria that trigger the work plan to run. |
Effectivity Details
| Field | Description |
|---|---|
| Start planned schedule on |
Option based on which the planned work schedule should determine its start date.
|
| Effective Start | Effective start date from when the planned work is scheduled to work. |
| Effective start reference |
Field value that should be used to determine the start date of the planned work. Effective start reference displays the list of fields from the table that is selected to create conditions for the work plan. For example, Printer [cmdb_ci_printer]. This field appears only when Field Value is selected from Start planned schedule based on. |
| Schedule |
Name of the schedule that should be used to calculate the start date of the work plan. This field appears only when Schedule is selected from Start planned schedule based on. |
| End planned schedule based on |
Determines the end date of a planned work schedule.
|