Set up work plans linked to task plan templates
Configure work plans and associate it with task plan templates.
Before you begin
Role required: sn_fsm_planned_wm.planned_work_admin
About this task
When the conditions specified in the Planned Work Schedule Task Template are met, tasks, cases, or incidents are created based on the defined task plan templates.
For example, to meet the monthly audit requirement of inspecting multiple stores of the same organization simultaneously, you should create individual planned work schedules for each audit. Link each schedule to a different task plan template. Include relevant conditions in each planned work schedule template to ensure the correct template is applied when generating tasks specific to each audit.