Create supplier tasks for the action plan

  • Release version: Australia
  • Updated March 12, 2026
  • 1 minute to read
  • Create supplier tasks for the affected KPIs in the action plan.

    Before you begin

    Role required: sn_kpi.admin

    Procedure

    1. Navigate to the Action plan items tab of the action plan.
    2. Select Create.
      The Crate new action plan item dialog box is displayed.Create new action plan item dialog box for creating supplier task
    3. Select Supplier task.
    4. Select the user who will be assigned this task.
    5. Select the action type required to close the task:
      • Mark complete
      • Play video
      • Upload documents
      • View link
    6. Select Create.
    7. In the form, fill in the required fields.
      Table 1. Create New Supplier Task form
      Field Description
      Supplier Name of the supplier
      Priority Priority of the supplier task to complete the action plan
      Assigned to User to whom the milestone tracking is assigned
      Due date Target date for the milestone
      Opened by User who created the supplier task
      Short description Brief description of the milestone
      Summary details
      Supplier case The case to which the task is related
      Expected start Expected start date of the supplier task
      Actual start Actual start date of the supplier task
      Actual end Actual end date of the supplier task
      Related task Tasks related to this supplier task
      Related KPIs KPIs related to this supplier task
      Related location Location in which this supplier task is to be performed
    8. Select Save to create and save the new supplier task.

    Result