Workflow of project risk assessment
Summarize
Summary of Workflow of Project Risk Assessment
This workflow explains how ServiceNow integrates Project Portfolio Management (PPM) with Governance, Risk, and Compliance (GRC) for effective project risk assessment. It guides project managers and risk specialists through identifying, assessing, and managing risks within projects and escalating them to enterprise risks when necessary.
Show less
Key Features
- Risk Identification: Project managers with the roles
itprojectmanagerandsngrc.businessuseridentify and add risks to projects, either by creating new risks or selecting from a risk library. - Risk Assessment Initiation: Assessors and approvers configured in the Project Integration Configuration form receive email notifications to assess risks. Only risks in Pending, Open, or Work in Progress states can be assessed.
- Risk Assignment: If stakeholders are designated as assessors, project managers must manually assign risks to the relevant stakeholders.
- Risk Assessment Execution: Risk assessors perform assessments via email links or by navigating to Advanced Risk Assessment tasks within the platform.
- Review and Elevation: Project managers review assessment scores in the Risk Assessment Summary and can elevate significant project risks to enterprise risks, which are copied to the enterprise risk register for further evaluation.
- Enterprise Risk Management: Elevated risks require assessment by enterprise risk managers who also hold the
sngrc.businessuserrole. Any reassessment triggers notification emails to ensure ongoing risk monitoring. - Risk Materialization and Issue Conversion: Should a risk materialize, project managers can convert the risk into an issue as part of the RIDAC (Risk, Issue, Decision, Action, and Change Requests) framework.
- Risk Visualization and Reporting: The project risk posture is visualized using a heatmap highlighting high impact and high likelihood risks, enabling prioritization. An aggregated risk score provides a consolidated metric for stakeholder reporting.
- Dashboards: The Project Risk Overview dashboard offers insights into overall project and enterprise risk postures, facilitating informed decision-making.
Key Outcomes
- Streamlined risk identification and assessment within projects ensuring timely risk awareness and management.
- Clear escalation path from project risks to enterprise risks, helping protect the organization from significant monetary or reputational losses.
- Defined roles and notifications ensure accountability and prompt action from project managers, risk assessors, and enterprise risk managers.
- Visualization tools such as heatmaps and dashboards support risk prioritization and effective communication to stakeholders.
- Integration with RIDAC supports risk mitigation by converting risks into actionable issues when necessary.
To understand the integration of Project Portfolio Management and Governance, Risk, and Compliance risk management capabilities, it is important to understand the workflow of project risk assessment.
Project risk assessment follows a sequence of steps. Sometimes, a risk is elevated to an enterprise risk after the risk is assessed. An enterprise risk is a risk that can cause monetary or reputational losses. It can jeopardize your ability to stay in business.
- A project manager identifies risks and adds those risks to a project. The manager can either create risks or add them from a library. The project manager has the it_project_manager and sn_grc.business_user roles. For more information, see Add risks for a project.
- The project manager then initiates risk assessment for the newly added risks. In
the Project Integration Configuration form, the assessors and approvers are
defined for the assessment. They get an email notification to assess the risks.
Note:You can only assess the risks that are in the Pending, Open, or Work in Progress state.
- If the Project Integration Configuration form has stakeholders selected as assessors, then the project manager must manually assign the risks to the relevant stakeholder.
- As a risk specialist, the risk assessor is notified about the new risks for assessment.
The risk assessor can use the link in the email notification to start the assessment. Alternatively, the risk assessor can navigate to to perform advanced risk assessment. See Advanced Risk Assessment.
- In the project risk form, the project manager reviews the Risk Assessment Summary section to view the risk assessment scores.
- If the project manager determines that the project risk has an impact on the
enterprise, then the project manager can elevate the risk to an enterprise
risk.Note:When a project risk is elevated to an enterprise risk, the project risk is copied from the project risk register to the enterprise risk register.
- If a risk is elevated to an enterprise risk, the enterprise risk manager is requested to assess the risk.
- The project manager views the enterprise inherent risk score and the enterprise residual risk score in the Risk Assessment Summary.
- As part of the Project Portfolio Management workflow, if a risk materializes and an action must be taken for this risk, then the project manager can convert the risk into an issue. For more information, see RIDAC (Risk, Issue, Decision, Action, and Request Changes) record entries for a project.
- The project manager can also view the project risk posture through the heatmap in the Risk Overview section on the project form. The heatmap displays high impact risks and high likelihood risks. With the heatmap, you can prioritize the risks that need immediate attention. The risks that are assessed contribute to the aggregated risk score. The aggregated risk score is a single score that can be reported to all the stakeholders. For more information, see Create a project.
- View the Project Risk Overview dashboard to understand the overall risk posture of project risks and of enterprise risks. For more information, see Project Risk Overview dashboard.