Risk matrix form

  • Release version: Zurich
  • Updated July 31, 2025
  • 1 minute to read
  • Safety team can use the risk matrixes to create and conduct risk assessments in the Health and Safety Workspace.

    For more information, see Conduct a safety risk assessment.

    Table 1. Risk matrix details
    Field Description
    Risk matrix details
    Number System-generated unique number for the risk matrix.
    Location Location that this risk matrix applies to.
    Short description Brief description about the risk matrix.
    Matrix grid Size of the grid to use, for example, 4*4 and 5*5.
    Active Option for making the matrix available for use. A risk matrix must be active to be used.
    Likelihood and severity
    Likelihood level Description of the likelihood level. These descriptions are used to populate the likelihood options on risk assessments where this matrix is used.

    The number of likelihood levels is based on the selected grid size. For example, for a matrix grid of size 5*2, there are five likelihood levels.

    Severity level Description of the severity level. These descriptions are used to populate the severity options on risk assessments where this matrix is used.

    The number of severity levels is based on the selected grid size. For example, for a matrix grid of size 5*2, there are two severity levels.

    Risk tolerance
    Risk tolerance Range, color, and description of the risk level. Select a range and color and enter a title for it.

    This risk tolerance range and title computes the risk level for a hazard on the Hazard assessment form, Risk analyses tab, and the risk assessment form header. For more information, see Assess a hazard and its risk levels.

    The value of the range is determined by multiplying likelihood level by severity level. For example, according to the grid in the following image, a hazard with a level 3 likelihood (Once per month) and a level 2 severity (Minor) has a risk tolerance of 3*2 = 6. The risk level for this hazard lies in the range 3 to 6, therefore, its risk level is displayed as Moderate.

    Risk matrix configuration showing calculation of risk ranges based on likelihood and severity values.

    Risk matrix preview
    Risk matrix preview Heatmap for visual representation of the risk matrix based on the defined levels, colors, and ranges in the real time.